Today is September 9, autumn has arrived, and tomorrow is China's traditional festival, the Mid Autumn Festival. We will eat traditional festival food, moon cakes, and enjoy the beautiful moon on the night of the Mid Autumn Festival. I hope Chinese people and friends all over the world will have a happy festival and weekend.
This week, we tested the completed integrated fresh air central air conditioning in the clean room, tested its power on, and tested its cooling and heating functions.
Because all the installation and component connection of the integrated air conditioner are completed in the factory, we can easily complete the commissioning work, test all the functions of the air conditioner in the factory, and do not need to disassemble the machine after the test, and directly send it to our customers after packaging.
After receiving the air conditioner, the customer can put it into use immediately after connecting the power supply and air duct,
In the test, we will start each compressor and heater separately to check whether they can operate normally and stably When the compressor is running, we need to observe the pressure gauges of the inlet and outlet of the compressor to check whether the compressor is working normally. Whether the refrigerant is sufficient
After all the functional tests are completed, we will also carry out necessary tests on the alarm protection system of the compressor today to ensure that the air conditioning system will not be seriously damaged due to some common faults
If you have questions and needs about air conditioning, please feel free to contact us. We have very professional and experienced Air Conditioning Engineers to provide you with 24-hour service and give you a perfect shopping experience